Consider the following project network and activity times (in weeks): Activity A B C D E F G H Time 5 3 7 6 7 3 10 8 How much time will be needed to complete this project

Respuesta :

codiepienagoya codiepienagoya
  • 04-07-2021

Answer:

Please find the attached file of the complete question:

Explanation:

Please find the attached file of the solution:

Critical Path:  ACH

Duration: 21

Because C is on the Critical Path, it cannot be postponed without causing the project to be delayed.

E is not on the critical path, thus it may also be delayed by two weeks without causing the project to be delayed.

[tex]D : ES : 6, EF : 10, LS : 7, LF : 11[/tex]

Ver imagen codiepienagoya
Ver imagen codiepienagoya
Answer Link

Otras preguntas

The resistivity of pure water is fairly high, 1.8 × 105 Ω·m, whereas the resistivity of sea water is a million times lower, 2 × 10-1 Ω·m. Why does the high salt
Please Answer this question! I would be very grateful!
What did freedom mean to mandela at the different stages of his life
please help me asap. i really need help just tell me the fallacies and ideas to write not the 300 word paragraph We must abolish Daylight Saving Time. The pra
What is the area of triangle ABC?
Can someone help me please
what is the domain of the following function: y=x^-5 + (x-1)
Pls help with that blue marked question! ASAP pls guys after a few hours I have exam so pls
What are the main strengths and weaknesses of each of the competitive strategies: home replication, multidomestic, regional, global, and transnational? What cha
Determin d/dx (x²+1) (7x-3) and d/dt(3t-2/5t+1)